Project name: Century Court, Phase I and II
Square footage: Phase I - 24,000 sq ft over seven units Phase II - 25,000 sq ft over five units
Site plan: Download Site Plan
Project completion date: Phase I completed in August 2015 and Phase II completed in August 2018
Building specifications: Portal frame construction, concrete floor, insulated steel wall cladding, insulated roof with lights, Eaves height from 6m to 7.2 m, electric roller shutter doors and yard area.
Occupancy at Westcott had been running at a rate of 95% for some time, this, coupled with the lack of grade A space in the region prompted the owners to move forward with a new speculative development scheme at the Park. Construction for Phase I of the development was completed in August 2015 and all seven units were fully let in just over a year after practical completion. Over 80% of Phase II was let within three months of completion.
The construction of new 13,250 sq ft clear span single storey industrial unit with associated yard and parking areas.
The first phase of the Building 6000 development set on 4.5 acres was let on a 10-year lease to Green Retreats.